  1. Framing: Schedule the rough framing contractor
  2. Frame the house all the way to the roof decking
  3. Roofing: Telephone the roofing contractor to confirm work schedule
  4. Install roofing felt, flashing and shingles
  5. Fireplace and Chimney: Telephonel masonry contractor to confirm work schedule
  6. Erect fireplace and chimney
  7. Plumbing: Telephone the plumbing contractor to confirm work schedule
  8. Install rough plumbing system
  9. Schedule the plumbing inspection
  10. Heating, Ventilation and Air Conditioning (HVAC): Notify HVAC contractor to confirm work schedule
  11. Install rough HVAC ductwork and equipment
  12. Schedule mechanical inspection
  13. Electrical: Telephone the electrical contractor to confirm work schedule
  14. Install rough electrical wiring and service panel
  15. Schedule electrical inspection
  16. Framing Inspection: Schedule the rough framing inspection
  17. Interior and Exterior Concrete/MasonryWork: Telephone concrete and masonry contractors to confirm work schedule
  18. Pour concrete floors, driveways, and walkways
  19. Ceiling Insulation: Telephone insulation contractor to confirm work schedule
  20. Install ceiling insulation
  21. Wall Insulation and Soundproofing: Notify insulation contractor to confirm work schedule
  22. Install wall insulation and soundproofing as required
  23. Inspection before covering walls: Schedule necessary inspections before drywall
  24. Interior Walls and Ceilings: Telephone drywall contractor to confirm work schedule
  25. Install drywall: hang, tape, float and texture if necessary
  26. Paint, Stain and Wallcoverings: telephone painting contractor to confirm work schedule
  27. Caulk exterior and interior walls where necessary
  28. Apply paint primer on the exterior and interior
  29. Apply interior paint, stain, wallcoverings
  30. Apply exterior paint, stain, preservatives
  31. Finish Floor Coverings: Telephone flooring contractors to confirm work schedule
  32. Install hardwood flooring
  33. Install resilient or ceramic tile
  34. Install padding and carpet
  35. Interior Finish and Trim: Telephone the finished carpentry contractor to confirm work schedule
  36. Install interior doors and hardware
  37. Install interior window and door trim
  38. Install baseboard base and shoe
  39. Install wall moldings, chair rails, etc.Install cabinets, countertops
  40. Install vanities, bars, soap dishes, mirrors
  41. Install closet shelves, poles, hardware
  42. Install stair treads, railings, balustersInstall mirrors, medicine cabinets
  43. Install tub and shower doors, rods etc.
  44. Finish Plumbing: Install plumbing fixtures and appliances
  45. Schedule the final inspection
  46. Finish HVAC: Install final HVAC equipment and test
  47. Schedule final inspection
  48. Finish Electrical: Install fixtures, appliances, outlet covers etc.
  49. Schedule final inspection
  50. Exterior Finish and Trim: Install window and door trim
  51. Install fascia, frieze and rake boards
  52. Install soffit and porch ceilings
  53. Install porch posts and railingInstall gable louvres, soffit vents, etc.
  54. Install garage door and door opener
  55. Install gutters and downspouts
  56. Landscaping: Schedule the landscaping contractor to start
  57. Finish grading, seeding, sodding and shrubbery
  58. Final Building Inspection: Inspect work of subcontractors and make punch list
  59. Review punch list (deficiencies) with contractors
  60. Re-inspect building after corrections and accept work
  61. Obtain lien waivers and approve final payment
  62. Telephone for final building inspection
  63. Conduct final walk-thru and notice any deficiencies
  64. Obtain occupancy permit
  65. Schedule final survey for bank loan
  66. Notify financial institution of completion - Schedule final appraisal
  67. Close on the construction loan and convert to new mortgage
  68. Notify insurance company of completion
  69. Switch insurance to home owner's policy
  70. Notify any other agencies of completion